The City / Community Redevelopment Agency and Ric-Man Construction continue work on the Hillsboro Boulevard Streetscape Improvements project and the re-construction of State Road 810 Hillsboro Boulevard between A1A and US-1. ...
The concrete slab and foundation system for the generator building have been poured. City crews have initiated tree removal operations for the planned berm and improved landscaping. The city's Grounds Maint...
Test piles and production piles to be driven during daytime hours.Earthwork operations to grade soil to the proper density and elevation. Relocation of utilities out of conflict with anticipated construction. Drai...